Have a task that is Fixed work where Duration=1h, Work=1h with a resource
assigned 100%.
When an actual of 0.5h is entered and Remaining Work is set to 0h then
Duration is set to 8h. Why is this? Should it not be 0.5h?
I've seen some postings on these. I've got difficulty trying to understand
some of the answered posts. Could someone please explain this in more detail
and shed some light.
Also is changing the Duration and Actual Work in the Task Usage view the
workaround to this?
Regards,
Joshua
Have a task that is Fixed work where Duration=1h, Work=1h with a resource
assigned 100%.
When an actual of 0.5h is entered and Remaining Work is set to 0h then
Duration is set to 8h. Why is this? Should it not be 0.5h?
I've seen some postings on these. I've got difficulty trying to understand
some of the answered posts. Could someone please explain this in more detail
and shed some light.
Also is changing the Duration and Actual Work in the Task Usage view the
workaround to this?
Regards,
Joshua