M
meg99
using 2003/2007 - I have 2 tasks (A & B) that show 21 days duration.
task B is a successor to A with a SS+7 days link. task A shows a bar
of 21 days but task B task bar only shows 7 days for the bar and it
does not start on the correct day. The constraint on both tasks is
ASAP. They both have the same calendar.
However, when I cycle the calendar for task B, task B then starts on
the correct day and the bar shows 21 days.
I have a couple of other tasks that show the same behavior.
I have never seen this before. Anybody have a clue what is going on?
meg99
task B is a successor to A with a SS+7 days link. task A shows a bar
of 21 days but task B task bar only shows 7 days for the bar and it
does not start on the correct day. The constraint on both tasks is
ASAP. They both have the same calendar.
However, when I cycle the calendar for task B, task B then starts on
the correct day and the bar shows 21 days.
I have a couple of other tasks that show the same behavior.
I have never seen this before. Anybody have a clue what is going on?
meg99