Thanks agian for the reply Mike. I realise that's what I have to do,
but my
original question was to know if there was a way of working out what
the lag
figure should be without manualy having to count the days.
Thanks
--
Robin
:
Hi Robin,
Double-click on the successor task and in the Predecessors tab, add a
lag to
the length of the delay you want and Project should honour that gap.
Mike Glen
Project MVP
Hi Mike,
I totally agree with you and 99% of the time I would do it using
the
methods
you mention. I have just one or two situations where I need to work
backwards. I generally put in a dependency where tasks don't
actually have
a
hard dependency, but I want to keep a consistent gap between tasks
if the
schedule slips. For example, resource levelled tasks. I want
everything in
future to push out and keep the tasks in the same order with the
same gap.
Perhaps there is a better way to achieve this?
Thanks again,
--
Robin
:
Hi Robin,
Welcome to this Microsoft Project newsgroup
I think you're putting the cart before the horse! You should not
type in
dates. Enter the Task Name, Duration and the Precedence (logic)
links.
Then let Project do what it is designed to do - create a schedule
for
you.
So, if Task 1 finishes on Monday, and you don't want Task2 to
start for a
week, you need to create a FS link with a lag of 1 week. You can
see
therefore that you have to know the duration gap to feed into
Project,
and
thus you don't need to calculate the gap.
FAQs, companion products and other useful Project information can
be seen
at
this web address:
http://project.mvps.org/faqs.htm
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
See
http://tinyurl.com/2xbhc for Project Tutorials
Does anyone know of an easy method of calculating the duration
between
the
finish of one task to the start of another task? E.g. Task 1
Finishes
on
Mon
1-1-08 while Task 2 Starts on Mon 8-1-08. Duration = 5 days.
Thanks