L
Laynne
Hi ,
I have gone through the threads but do not find an answer to my specific
problem.
I am in the earthmoving business.Weird as it may sound but my tasks is
shifting of ground and I do not have a completion date.My completion date is
dynamic and can change based on the amount of resources " dozers" I want to
allocate to the project.
Inputs :
Task = Each block of ground is a volume lets say 30 000 tons
Resource =I have a dozer that can mine @ 300 tons / hour.
Duration = 30 000/300 = 100 hours , which is then used to update my schedule
finish date.
Objective of this excercise :
I want to adjust the tons / hour value to determine completion date.
I have 475 blocks that needs to calculated and linked to determine my final
completion date.
Maybe the question is stupid , but I would really appreciate a solution
Thanks in advance![Smile :) :)](data:image/gif;base64,R0lGODlhAQABAIAAAAAAAP///yH5BAEAAAAALAAAAAABAAEAAAIBRAA7)
I have gone through the threads but do not find an answer to my specific
problem.
I am in the earthmoving business.Weird as it may sound but my tasks is
shifting of ground and I do not have a completion date.My completion date is
dynamic and can change based on the amount of resources " dozers" I want to
allocate to the project.
Inputs :
Task = Each block of ground is a volume lets say 30 000 tons
Resource =I have a dozer that can mine @ 300 tons / hour.
Duration = 30 000/300 = 100 hours , which is then used to update my schedule
finish date.
Objective of this excercise :
I want to adjust the tons / hour value to determine completion date.
I have 475 blocks that needs to calculated and linked to determine my final
completion date.
Maybe the question is stupid , but I would really appreciate a solution
Thanks in advance