W
Wendy
Using a Fixed Work task, work, duration and units have been calculated
using Generic resources. Subsequently, Generic resources were replaced
with actual resources and durations changed. Both the Generic and
Actual resources utilized the same calendar and no time is listed as
non-working in either calendars. What could be the cause of the
modification of the duration calculation?
using Generic resources. Subsequently, Generic resources were replaced
with actual resources and durations changed. Both the Generic and
Actual resources utilized the same calendar and no time is listed as
non-working in either calendars. What could be the cause of the
modification of the duration calculation?