Duration calculation problem in PWA

S

Stumped

Using PS 2003 SP2a.

All duration fields in the project center, task page, assignments page,
etc., do not calculate the same duration as shown in the project plan when
opened in Microsoft Project with SP2 applied.

For example, a one day task, or a task with 480 min duration, is calculated
as 1.14 days in all duration fields in PWA. This is most serious on the
summary level. A 100 day duration project might show a duration of 115 days
in PWA. Work is calculating correctly.

All other timing data seems to be correct. Start and finish, etc.

Any ideas?
 
P

paul conroy

Open Proj Pro, then Tools\Options\Calendar from the menu bar.

Check Hours per Day is equal to 8 Hours.

HTH

Paul
 
S

Stumped

Thanks Paul, but nope, the durations in Pro is different that what show in
all related pages in PWA. Task, project center, project, assignment.
 