J
Jim
When I enter a start date (9/3/03) and enter a duration of 6 weeks, MSP
calculates the finish date to 10/6/03. If I count the weeks manually (Wed.
to Wed. X 6), I come up with a finish date of 10/15/03. The six weeks is
for delivery of a part so work resources are not being used. Should I be
using a special calendar for this to come up with my manual calculation?
TIA
calculates the finish date to 10/6/03. If I count the weeks manually (Wed.
to Wed. X 6), I come up with a finish date of 10/15/03. The six weeks is
for delivery of a part so work resources are not being used. Should I be
using a special calendar for this to come up with my manual calculation?
TIA