R
reza
Hi All,
Why after i enter values in OT Field, duration will change it?
for example...
Task A have 1day duration, then i enter values in OT field for 4
hours..after that duration will change into 0.5 day...
Also If i enter values actual work for example 4hrs...then actual overtime
work will automatically fill become 2hrs...
need your explanation
thanks
Why after i enter values in OT Field, duration will change it?
for example...
Task A have 1day duration, then i enter values in OT field for 4
hours..after that duration will change into 0.5 day...
Also If i enter values actual work for example 4hrs...then actual overtime
work will automatically fill become 2hrs...
need your explanation
thanks