Duration changes, Work changes are inconsistently

M

Michael

We use Project 2003 Fixed Duration - Not effort driven

When changing the duration of a task, most of the time it will update work
as expected. But too often to be a quirk, when duration is changed it will
not change work, and I can't seem to find a pattern why. Is there Project
logic for why these cases happen?
 
D

Darrell

Michael,

If the task is fixed duration, and there is a resource assigned, it should
recalculate the work. It will not recalculate the work for a task without a
resource assigned because it doesn't know the units. Got resources?

Darrell
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top