C
Chris
I have a project that I am currently tracking using Project 2003. However, when I do my leveling it is changing the duration dates of the completed tasks from i.e. 021104 to 021304 for both the start and the finish dates. The completed percentage is 100%; how do I lock these dates into Project so that it does not change the dates when I level for the tasks that are not completed?