M
Mark E. Read
Helping a client with a weekend calendar issue, I may need some more help...
This is Project 2007 pre-SP1 (no updates)
We've got two 100 hour tasks lasting through a weekend, and the work (100
hrs), resource units (100%) and start (Friday) and finish (Monday) dates all
agree, but the duration seems to indicate a strange number (like 12 days or
2.5 weeks) rather than the expected three days indicated by the difference
between start and finish.
The standard day is 8 hours in Tools>Options.
The task is using a calendar set to working time from 12AM to 12AM, and the
calendar was added AFTER the plan was built.
Any thoughts? I have a screen capture of the duration, work start and
finish to illustrate my conundrum if anyone would like to see. Is there
something broken with the duration display? Is the calendar exception
throwing off bad data? Am I missing something?
Thanks!
This is Project 2007 pre-SP1 (no updates)
We've got two 100 hour tasks lasting through a weekend, and the work (100
hrs), resource units (100%) and start (Friday) and finish (Monday) dates all
agree, but the duration seems to indicate a strange number (like 12 days or
2.5 weeks) rather than the expected three days indicated by the difference
between start and finish.
The standard day is 8 hours in Tools>Options.
The task is using a calendar set to working time from 12AM to 12AM, and the
calendar was added AFTER the plan was built.
Any thoughts? I have a screen capture of the duration, work start and
finish to illustrate my conundrum if anyone would like to see. Is there
something broken with the duration display? Is the calendar exception
throwing off bad data? Am I missing something?
Thanks!