Å
åŠæ–°ä¸æ—§
I have a duration disaccord issue with Project Server 2007. The enterprise
calendar we are using defines the daily working hour is 7.5hrs. In case of a
task duration is 1 day:
- The duration shown on Project professional is 1day
- But the duration shown on PWA_My Tasks page is 0.94day
- Further, the 'Total Work' field on <Assignments detail> view is 7.5hrs.
How can I solve this problem?
Thanks in advance,
JJin
calendar we are using defines the daily working hour is 7.5hrs. In case of a
task duration is 1 day:
- The duration shown on Project professional is 1day
- But the duration shown on PWA_My Tasks page is 0.94day
- Further, the 'Total Work' field on <Assignments detail> view is 7.5hrs.
How can I solve this problem?
Thanks in advance,
JJin