A
Alan Saxon
I have recently installed the latest version of project. All my days are
entered as whole days. The owning task displays the total days with a decimal
i.e.
Task Name Duration
Install m/c 50.4
Write requirements 10
Build m/c 10
Install 10
Commission 10
Accept 10
entered as whole days. The owning task displays the total days with a decimal
i.e.
Task Name Duration
Install m/c 50.4
Write requirements 10
Build m/c 10
Install 10
Commission 10
Accept 10