J
jzis
I have the following plan:
TASK NAME DURATION
Testing 5 days
Pre test 10 days
Pre test 5 days
Pre test 10 days
Pre test 5 days
The Summary task (Testing) duration does not properly add the sub task
durations. How do I get is so that "Testing" properly adds to 30 days?
Thank you.
- - - jzis
TASK NAME DURATION
Testing 5 days
Pre test 10 days
Pre test 5 days
Pre test 10 days
Pre test 5 days
The Summary task (Testing) duration does not properly add the sub task
durations. How do I get is so that "Testing" properly adds to 30 days?
Thank you.
- - - jzis