andre
I have a task that has started out with a duration say 200h. I assign 5 men
which would give me 40h/man. I enter the times worked in the time sheet.
view-task usage.
Now I go through the two weeks and at the end of the two weeks I realize the
work is only 90% done. So up to speed. I have entered in the times, now this
is times actually worked. So %work complete and the %complete show 100% but
the task is really only 90% complete but the amount of original work
scheduled is 100% complete. So I need the men to keep working. If I change
the %complete field to 90% then it changes the both the work and %pecent
complete to 90% but decreases the time fields in the task usage. But these
men worked a full day.
So in short, I guess, I need the duration to increase when I change the
percent complete field. Do I have to change that manually?
I am really confused.
Thanks
Andre
which would give me 40h/man. I enter the times worked in the time sheet.
view-task usage.
Now I go through the two weeks and at the end of the two weeks I realize the
work is only 90% done. So up to speed. I have entered in the times, now this
is times actually worked. So %work complete and the %complete show 100% but
the task is really only 90% complete but the amount of original work
scheduled is 100% complete. So I need the men to keep working. If I change
the %complete field to 90% then it changes the both the work and %pecent
complete to 90% but decreases the time fields in the task usage. But these
men worked a full day.
So in short, I guess, I need the duration to increase when I change the
percent complete field. Do I have to change that manually?
I am really confused.
Thanks
Andre