S
Steve Scott
I need to run a query in an Access mdb which lists tasks across multiple
projects that have durations >10 days within the next month. Exporting from
MS Project to Access will only do so in a numerical format eg "4200" for 1 x
7 hr day.
How can I convert these values into days easily ie as they were displayed in
the original plans bearing in mind that some of the plans had 7hr working
days and others 8hr working days?
Alternatively is there a way I can run the export map and get the displayed
value (ie in days) to be exported instead of the eg 4200 format?
projects that have durations >10 days within the next month. Exporting from
MS Project to Access will only do so in a numerical format eg "4200" for 1 x
7 hr day.
How can I convert these values into days easily ie as they were displayed in
the original plans bearing in mind that some of the plans had 7hr working
days and others 8hr working days?
Alternatively is there a way I can run the export map and get the displayed
value (ie in days) to be exported instead of the eg 4200 format?