Hi Mike,
Thanks for the test of 2000. It's been awhile since I used 2000 and
didn't have time to drag the old computer out of moth-balls.

Julie
:
Yes, 2000 has the same facility. You can also remove the odd one
by re-typing the duration.
Mike Glen
Project MVP
JulieS wrote:
Hi Jack,
No it shouldn't. The question mark just shows that the task has
an estimated duration. Because you didn't enter the duration
initially, the question mark remains even after the recalculation.
You may supress the display of the question mark by going to Tools
--> Options. On the Schedule tab, uncheck "Show that tasks have
estimated durations". You may also want to uncheck "New tasks
have estimated durations." [Note: Those are options in Project
2003, I believe they were in 2000 as well, but I don't have 2000
handy to check right now.]
Hope this helps. Let us know how you get along.
Julie
:
I create tasks and enter the number of work hours in
MSProject2000. The calculated duration hours remains with a
question mark. Will that create a problem if I don't physically
remove the question marks? --
Jack