duration format type

S

slippymississippi

Any leaf nodes in the task list appear to be set to 7. All other nodes
appear to be set to 21. Looking at the PSD schema, values of 7
represent "days." However, the unit of measure in TASK_DUR and
TASK_ACT_DUR is still set to 1/10 of a minute. Does TASK_DUR_FMT ever
change to something besides 7? If so, does it ever change the
representation of the TASK_DUR data to units other than 1/10 of a
minute?
 
R

Ray McCoppin

I think that the Task_DUR_FMT is how these are displayed in the project
plan(Project Pro), the actual duration fields are alway stored in the DB as
1/10ths of minutes.

Hope this helps.
 