Hello-
We want to exclude closing tasks from our calculated measurement of
duration. For example, our stoplight indicators are red, yellow, and green
based on baselined duration vs. actual duration.
We consider the project to have met the commitment date at the end of our
"executing" phase. But, we want to track closing tasks within the project in
order to properly allocate resources from the enterprise resource pool.
So, I created a custom field for task type to show which phase the task is
in. I want to measure the baseline duration vs the actual duration for all
tasks that exclude task type of closing.
I am not a programmer and I am struggling with this. Any thoughts? Thanks
so much!
We want to exclude closing tasks from our calculated measurement of
duration. For example, our stoplight indicators are red, yellow, and green
based on baselined duration vs. actual duration.
We consider the project to have met the commitment date at the end of our
"executing" phase. But, we want to track closing tasks within the project in
order to properly allocate resources from the enterprise resource pool.
So, I created a custom field for task type to show which phase the task is
in. I want to measure the baseline duration vs the actual duration for all
tasks that exclude task type of closing.
I am not a programmer and I am struggling with this. Any thoughts? Thanks
so much!