E
Eric Stevens
All,
Here are the three formulas I am trying to calculate.
Proj Completion Time Variance(Enterprise Proj Duration 1)
= ProjDateDiff([Enterprise Project Date1],[Start])
Client Delivery Expected Variance(Enterprise Proj Duration
2) = ProjDateDiff([Enterprise Project Date2],[Finish])
On Time Delivery Variance(Enterprise Proj Duration 3) =
ProjDateDiff([Finish],[Baseline Finish])
The third one should equal Finish Variance. My results are
0 in the top level with error shooting down the tasks. I
am just trying to get some durations between custome
dates. Can anyone help?
Thanks,
Eric
Here are the three formulas I am trying to calculate.
Proj Completion Time Variance(Enterprise Proj Duration 1)
= ProjDateDiff([Enterprise Project Date1],[Start])
Client Delivery Expected Variance(Enterprise Proj Duration
2) = ProjDateDiff([Enterprise Project Date2],[Finish])
On Time Delivery Variance(Enterprise Proj Duration 3) =
ProjDateDiff([Finish],[Baseline Finish])
The third one should equal Finish Variance. My results are
0 in the top level with error shooting down the tasks. I
am just trying to get some durations between custome
dates. Can anyone help?
Thanks,
Eric