Duration getting changed automatically.

S

Sumit

Hi...

I have tasks with task type as fixed duration.

While importing data for assignments for that task I notice that the
DURATION gets AUTOMATICALLY changed in 2 cases:-

1) When I am importing actual effort for assignment
or
2) When I import actual start date for that assignment( assignment doesn't
have actual finish date as of now).

I am not able to find the logic why MSP is doing that.

Any help or insight into the behavior is really appreciated!!

Thanks a lot in advance!!!
 
S

Steve House

Are you IMPORTING the data or manually inputting it? If you're importing
it, from what and how? Do the tasks in question have any constraints such
as Must Finish On or Must Finish No Later Than?
 