M
Manmeet Chaudhari
I have project server 2003.
I had created a template, which had resources and standard working calendar.
This template had total duration of 130 days
Now I want to published a project using this template but with modifications
as follows
1. Project Calendar- 7 days working, 10hours a day
2. Resource Calendar- 7 days working, 10 hours a day
However when I published my project the duration went to 235 days. The
calendar which I am using is a global calendar. Kindly suggest what I am
missing. Why is my duration going haywire.
Manmeet Chaudhari
I had created a template, which had resources and standard working calendar.
This template had total duration of 130 days
Now I want to published a project using this template but with modifications
as follows
1. Project Calendar- 7 days working, 10hours a day
2. Resource Calendar- 7 days working, 10 hours a day
However when I published my project the duration went to 235 days. The
calendar which I am using is a global calendar. Kindly suggest what I am
missing. Why is my duration going haywire.
Manmeet Chaudhari