Duration in "ewks"

C

Corey

Does anyone know what a duration of "ewks" represents?
When a task has this duration, I can't assign a calendar
to it and it appears to ignore the project calendar I
chose in the Project Information dialog box (it's ignoring
holidays).

Thanks,

Corey
 
D

Dale Howard [MVP]

Corey --

The designation "ewks" refers to "elapsed weeks." An elapsed week is seven
24-hour days, thus, it will ignore the project calendar. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 