Duration in fraction.

V

Vinayak Bhat

1) I am getting duration in fraction. How do I correct them?

2) If project is on hold for 3 months and no activity is carried out during
this period in the middle of the project and it resumes later, how do I
display in the project plan?

Thanks very much in advance.

Vinayak Bhat
 
J

Jim Aksel

1. Fractional durations (1.113 days) are typically the result of units
assignments and work. For example, dividing 20 hours of work among 3 men.
Since work=duration x units, I usually split the screen (Window/Split) and
display Resources in the bottom pane. I adjust Work and units% to achieve
the desired results of whole days or the desired fraction (2.5 days), etc.
The solution may vary depending on the task type of fixed work, units,
duration and if it is effort driven.

2. Suspended calendar. Set a status date such as 28 AUGUST 2007. Make sure
all your %completes, etc. are correct to the status date. That is, no
incomplete work to the left of this date and no actual starts to the right of
this date. So, your schedule is now "up to date." Make sure you have
correct logic to drive your incomplete work based on predecessors, not hard
coded dates.

Suppose you want to be "silent" on the project from 28 AUGUST until 15
JANUARY 2008. What you want to do is reschedule all work that is in progress
as of 28 AUGUST plus push out unstarted work.

Tools/Tracking/Update Project. Select "Rescheule uncompleted work to start"
In the dropdown box, select the project resume date from the drop down. In
this case 15 JAN 2008. Select "Entire Project" then click OK.

All remaining work will move the right leaving a hole between 28 AUG and 15
JAN.
Be careful to manually adjust any hard coded dates as well in case your
schedule logic did not move them for you.
--
If this post was helpful, please consider rating it.

Jim
It''s software; it''s not allowed to win.

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
M

Mike Glen

Hi Vinayak ,

Welcome to this Microsoft Project newsgroup :)

Fractions are often caused by a mis-match between calendar settings and the
Options settings. You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 
V

Vinayak Bhat

Thanks very much indeed.

It works. However summary tasks still show fractions.

How do i update these summary tasks.

Regards
Vianyak Bhat
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top