Nope - the work is the amount of effort the resource will expend. The
duration is the amount of time over which he will expend it. The "?"
indicates an estimated duration, NOT an estimated work, because the duration
field is a time measurement, not a work measurement. Remember that "work"
in MS Project is what is called "effort" in most other project management
contexts to better indicate it is not a time measurement. (Project, OTOH,
uses the term "effort" to indicate the rate at which work is performed.) Of
course, all durations are estimates until the work is actually done but I
think of the question mark as a reminder flag telling me I should come back
and take another look at that task's timing when I have more information to
go on.
The difference between a work estimate and a duration estimate is
illustrated by the difference between work and duration itself. I have a
task that requires 40 man-hours of work. If my resource devotes his full
attention to it he'll do it over the course of 40 hours of duration. But he
might be juggling two things at once and is only able to devote half his
energy to this particular task. He still has to generate 40 man-hours worth
of output, but now it'll take him twice as long. 40 man-hours of work at
50% effort means 80 hours of duration. Or maybe he's working full speed and
I get another guy to work alongside him. Now the total effort applied to
the task is 200% (2 people @ 100% each) and the 40 man-hours of work gets
done in 20 hours of duration because we get 2 hours of work output for each
hour of time put in.
If you make an analogy to a trip in a car, work is the distance to be
traveled, effort (assignment %) is the speed you're going, and duration is
the time it takes to get there.
--
Steve House [MVP]
MS Project Trainer/Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs