I would like to show the duration of tasks includig week ends even if no
resource is going to work during those days. For example, I have a
requirement for a task that has to last 10 days, but 10 calendar days. As my
calendar excludes the week ends, project considers 10 workind days excluding
week ends and the calendar duration is longer than 10 days.
How can I solve that issue? Can I insert a formula? or is there another way?
thanks