P
Peter Williams
I have a simple test project. ASAP, Fixed Unit Effort Driven tasks. I
assigned a resource and then updated the Actual work for that resources via
PWA. I put in 4 hours work on the same day the work was scheduled.
After accepting updates..I expected to see 50% complete on the Gantt.
Instead I see 67% complete, the duration has increased to 1.5 days from a
day. And therefore the following dependent tasks have been pushed a bit.
Is this the expected behavior ?
assigned a resource and then updated the Actual work for that resources via
PWA. I put in 4 hours work on the same day the work was scheduled.
After accepting updates..I expected to see 50% complete on the Gantt.
Instead I see 67% complete, the duration has increased to 1.5 days from a
day. And therefore the following dependent tasks have been pushed a bit.
Is this the expected behavior ?