A
agarwalp
Hi,
I am a newbie. I was just to replicate a project from
http://www.mousetrax.com/pub/Bridge15.zip
made by MVP Mike Glen.
I have two question here.
1. The task "Surveys" has Duration 3.1 wks but the Start date is 3 Mar
and Enddate is 7 May. How can this happen? The only way i can think of
is there might be some vacation period between the two dates. If that
is the case how can i define the vacation days?
2. Also when i assign resources the difference is as below
In sample project-> Surveyors 500% 428.57h, Mike 100% 85.72h and Jane
100% 85.72h
In my project -> Surveyors 500% 428.72h, Mike 100% 120.4h and Jane 100%
120.4h
I am really not able to understand where am i doing wrong. Please help
me.
I am a newbie. I was just to replicate a project from
http://www.mousetrax.com/pub/Bridge15.zip
made by MVP Mike Glen.
I have two question here.
1. The task "Surveys" has Duration 3.1 wks but the Start date is 3 Mar
and Enddate is 7 May. How can this happen? The only way i can think of
is there might be some vacation period between the two dates. If that
is the case how can i define the vacation days?
2. Also when i assign resources the difference is as below
In sample project-> Surveyors 500% 428.57h, Mike 100% 85.72h and Jane
100% 85.72h
In my project -> Surveyors 500% 428.72h, Mike 100% 120.4h and Jane 100%
120.4h
I am really not able to understand where am i doing wrong. Please help
me.