B
Bill K
If I assign a new calendar to a resource that contains a
work schedule that includes a 10 hour work day the
duration of the resource is not adjusted. Spicificaly, If
a task has a duration of 5 days and 40 hours of work,
using the standard calendar if the task started on the 1st
it would end on the 5th. When I assign a 50 oury a week
calendar to the resource the end date shortens but the
duration remains at 5 days. Can someone please explain why
the duration is not shortened to 4?
work schedule that includes a 10 hour work day the
duration of the resource is not adjusted. Spicificaly, If
a task has a duration of 5 days and 40 hours of work,
using the standard calendar if the task started on the 1st
it would end on the 5th. When I assign a 50 oury a week
calendar to the resource the end date shortens but the
duration remains at 5 days. Can someone please explain why
the duration is not shortened to 4?