M
Mike
I have a Fixed Work task that will take 100 hours of Work. The resource is a
piece of equipment that is allocated at 100% Units on the 24 Hours Base
Calendar.
The Duration, however, is calculated at 12.5 days in the Task view, which is
what you'd expect for the Standard Base Calendar (8 hours/day). The Duration
should be just over 4 days for this resource at 24 hours/day, which is how it
appears in the Gantt chart (blue bar extends over a four day period).
What could be causing this? Thanks.
piece of equipment that is allocated at 100% Units on the 24 Hours Base
Calendar.
The Duration, however, is calculated at 12.5 days in the Task view, which is
what you'd expect for the Standard Base Calendar (8 hours/day). The Duration
should be just over 4 days for this resource at 24 hours/day, which is how it
appears in the Gantt chart (blue bar extends over a four day period).
What could be causing this? Thanks.