Duration of Capacity

M

Micah

When working with OLAP Cubes in 2007, does Capacity only calculate one year
out?
I have built a cube with date ranges of the earliest project start date and
the latest project finish date. My projects go well into 2012. While changing
some parameters in my pivot table, I noticed that Capacity for my resources
suddenly ends in Feb. of 2011. The pivot table and chart show the work for
these resources all the way to 2012. So, why does capacity not go to 2012 as
well. My only guess is that it only calculates for one year. Can anyone
confirm this? Is there a way to adjust this to cover three years out, or
until the latest project finish date?
Thanks
 
J

Jack Dahlgren MVP

You control resource capacity by going to PWA / Server Settings / Additional
Server Settings and adjusting the Resource Capacity Settings.

-Jack Dahlgren
http://zo-d.com/blog
 
J

Jack Dahlgren MVP

No problem. I don't know why they didn't put that under the cube settings
where people could find it.

-Jack
 