C
confused
Hi,
I am new to project server having used MS Project quite frequently.
With MS project, I would weekly update the percentage complete and re-level
the project, and then make any necessary adjustments to the plan to bring it
back (eg assigning more resources etc) in if the levelling had pushed the
date out.
With project server, individuals enter their own remaining work. the effect
on my project is to increase the duration of the task in question, and not
have any indication od which tasks have changed. In reality, if a task takes
longer than expected, the last thing i would do to the plan would be to
incease task duration, more lilely i would increase number of resources on
the task etc. How can i stop project server from deciding for me what action
to take on the plan?
Many thanks in advance for any help
I am new to project server having used MS Project quite frequently.
With MS project, I would weekly update the percentage complete and re-level
the project, and then make any necessary adjustments to the plan to bring it
back (eg assigning more resources etc) in if the levelling had pushed the
date out.
With project server, individuals enter their own remaining work. the effect
on my project is to increase the duration of the task in question, and not
have any indication od which tasks have changed. In reality, if a task takes
longer than expected, the last thing i would do to the plan would be to
incease task duration, more lilely i would increase number of resources on
the task etc. How can i stop project server from deciding for me what action
to take on the plan?
Many thanks in advance for any help