I
Ivor Davies
I was wondering if anyone could answer a few questions for me regarding
administrative projects?
My manager has created an administrative time project for our department to
report on non-project time (support & maintenance) etc.
When resources update their task information the either the FINISH DATE or
the DURATION changes in the project plan, so my manager has to manually
adjust back to the proper value.
Also for some reason the status indicator that we developed changes from
green to yellow (and sometimes red) when time is updated into the admin
project plan.
Does anyone have any insight on this?
Do we need to make any changes to the tasks in the plan (i.e. - effort
driven)?
Please advise - Thank You
administrative projects?
My manager has created an administrative time project for our department to
report on non-project time (support & maintenance) etc.
When resources update their task information the either the FINISH DATE or
the DURATION changes in the project plan, so my manager has to manually
adjust back to the proper value.
Also for some reason the status indicator that we developed changes from
green to yellow (and sometimes red) when time is updated into the admin
project plan.
Does anyone have any insight on this?
Do we need to make any changes to the tasks in the plan (i.e. - effort
driven)?
Please advise - Thank You