I am sure this is a stupid question but why do my durations default to xx.94
all the time?? I can't figure out what I am doing that makes them not
calculate at a whole number.

Thanks!
 
J

JulieS

Hi Laurel,

My guess would be that your project calendar's definition
of working time is different from the definition of the
number of hours in a day set in Tools --> Options on the
Calendar tab.
I have never seen it make those calculations in new
tasks, but I certainly have seen odd calculations if the
definition of the number of hours in a day is change
after tasks have been added.
Hope this helps.
Julie
 