F
fkartal
Hi all,
I have an ERP db on SQL 2K it has some tables about project and its tasks.
When creating new Ms Project and adding its tasks duration couldnot be
exported correctly.
As a simple Im assigning
Start Date,
Duration, Precedence and Finish Date to the new task. At the end the
duration calculated as almost zero day but really it would be 10 day.
Thanks for any comment
I have an ERP db on SQL 2K it has some tables about project and its tasks.
When creating new Ms Project and adding its tasks duration couldnot be
exported correctly.
As a simple Im assigning
Start Date,
Duration, Precedence and Finish Date to the new task. At the end the
duration calculated as almost zero day but really it would be 10 day.
Thanks for any comment