barrymoss
The company I work for operates on a 9/80 work schedule. Monday through
Thursday of every week we work 9 hrs. and alternating Fridays we are off work
and the other Friday we work 8 hrs. I incorporated this into every resource
in our resource pool and then into the shared calendar amongst all of the
projects. One of the questions I have is that when I go into options and then
the calendar view it asks for the number of hours a week. I need to this to
be 44 one week and 36 the other, how do I bypass this? This seems to
override what I set forth in the calendars. Here is what I think is
happening on the weeks we work 36 hours project calculates that when we work
9hr. days it is actual only utilizing 87% of the resource for the week and
then when the resource works the 44 hour week is utilizing 113% of allocation
which shows an overallocation of the resource. Also, on the 36 hour weeks
when you the duration seems to be off. For instance this week is a 36 hour
week and we have a task for 4/28 with a one day duration, but is does not
finish until 4/29. I went into the resource usage and found that 8 hours
have been spread against 4/28 and 1 hr. against 4/29 and when I move the one
hour back to 4/28 it over allocates the resources for the day. I went back
and check the calendars and everything is on order. Is Project trying to
pull my resource against the set 40 hrs? week to shrink it 87% utilization?
When I initially add the resource it tells they are working 9 hrs. for one
day, but it spreads it out over 2 calendar days. Any ideas?
Thanks in advance,
Barry
Thursday of every week we work 9 hrs. and alternating Fridays we are off work
and the other Friday we work 8 hrs. I incorporated this into every resource
in our resource pool and then into the shared calendar amongst all of the
projects. One of the questions I have is that when I go into options and then
the calendar view it asks for the number of hours a week. I need to this to
be 44 one week and 36 the other, how do I bypass this? This seems to
override what I set forth in the calendars. Here is what I think is
happening on the weeks we work 36 hours project calculates that when we work
9hr. days it is actual only utilizing 87% of the resource for the week and
then when the resource works the 44 hour week is utilizing 113% of allocation
which shows an overallocation of the resource. Also, on the 36 hour weeks
when you the duration seems to be off. For instance this week is a 36 hour
week and we have a task for 4/28 with a one day duration, but is does not
finish until 4/29. I went into the resource usage and found that 8 hours
have been spread against 4/28 and 1 hr. against 4/29 and when I move the one
hour back to 4/28 it over allocates the resources for the day. I went back
and check the calendars and everything is on order. Is Project trying to
pull my resource against the set 40 hrs? week to shrink it 87% utilization?
When I initially add the resource it tells they are working 9 hrs. for one
day, but it spreads it out over 2 calendar days. Any ideas?
Thanks in advance,
Barry