Hi Guys,
Using PS 2007, need your help.
In my project server, i already have project calendar which i already edited
with holidays. There is a new project..for task A start/finish i.e 1-10 feb
so duration is 10 days. But because in project calendar for Feb 5th is non
working day, so i set resource calendar for Feb 5th is working day.
But when i looked up in Gant Chart summary of that task is 9 days not 10 days.
when i looked in task usage view...for task A duration is 10 days but not
for summary. The summary show only 9 days.
I repeat...Task A is correct 10 days or 80 hours. But summary task is 9 days.
(wish you understand with my explanation)
what i want to ask..is it like that behaviour of MS Project....
thanks
reza
Using PS 2007, need your help.
In my project server, i already have project calendar which i already edited
with holidays. There is a new project..for task A start/finish i.e 1-10 feb
so duration is 10 days. But because in project calendar for Feb 5th is non
working day, so i set resource calendar for Feb 5th is working day.
But when i looked up in Gant Chart summary of that task is 9 days not 10 days.
when i looked in task usage view...for task A duration is 10 days but not
for summary. The summary show only 9 days.
I repeat...Task A is correct 10 days or 80 hours. But summary task is 9 days.
(wish you understand with my explanation)
what i want to ask..is it like that behaviour of MS Project....
thanks
reza