G
Gary
Hi,
I'm inserting some splits in a number of tasks in my project file, but would
like the overall duration to include the split time, which at present it
doesn't seem to do, the reason being that during the split we will still be
working on the task, paper work, tenders that sort of thing.
Is this possible.
Many thanks
I'm inserting some splits in a number of tasks in my project file, but would
like the overall duration to include the split time, which at present it
doesn't seem to do, the reason being that during the split we will still be
working on the task, paper work, tenders that sort of thing.
Is this possible.
Many thanks