Duration Units

F

Frances

Can anyone tell me how to re=set the duration units from
days to hours? I have used the Tools, Options, Schedule
path and set hours as default but only headline tasks and
not subtasks get altered.

Many thanks for any assistance!
 
J

Jan De Messemaeker

Tools, Macro, macros, Format_Duration, Run
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA
32-495-300 620
 