kat8of10
Hi
My enviornment is MS Project server 2003. We have been working with it
for about a year and finally are seeing some stabilization - my
question is regarding duration variance between the project center and
MS Project plans. For example
Line 20 has Duration of 2 days and 10 hours of Work in MS Project, but
in PWA it shows 1.78 day Duration and 10 hours of work (no resource
assigned).
We had at one time been working with changing the default standard
times and this paritcular project has
as it's defaultTools/Options)
Default start time 5AM
Default end time 5PM
Hours per day 8
Hours per week 40
Days per month 20
The enteprise defaul shows currently shows
default start time 9AM
Default end time 5PM
Hours per day 9
Hours per week 45
Days per month 20
Any help is appreciated
thank you
Kathleen
My enviornment is MS Project server 2003. We have been working with it
for about a year and finally are seeing some stabilization - my
question is regarding duration variance between the project center and
MS Project plans. For example
Line 20 has Duration of 2 days and 10 hours of Work in MS Project, but
in PWA it shows 1.78 day Duration and 10 hours of work (no resource
assigned).
We had at one time been working with changing the default standard
times and this paritcular project has
as it's defaultTools/Options)
Default start time 5AM
Default end time 5PM
Hours per day 8
Hours per week 40
Days per month 20
The enteprise defaul shows currently shows
default start time 9AM
Default end time 5PM
Hours per day 9
Hours per week 45
Days per month 20
Any help is appreciated
thank you
Kathleen