Duration view in PWA

S

ShaharF

Hi All ,
For some reason my project's duration in PWA is lower than the one I see
in project professional 2003 .
I assume it has to do with the settings on PWA for a working day length ,
but couldn't resolve this ....
Any advice ?
Thank you ,
Ben
 
M

MichelleDalco

Hello,

Did you check the resource calendar(s) and the project's calendar in MS
Project 2003. It may be different then the Enterprise Calendar or the
Enterprise Resource's calendar.
 