What's happening here?
Thanks,
Glenn
:
Is the checkbox on the calculation page "Updating Task Status
Updates
Resource Status" on or off? For convenience assume the task in
your
scenario started Monday, was to end Friday and the default
Standard calendar
is in charge. An the first day, when you entered 10% work
complete, with it
on it, Project also sets the Actual Duration to 4 hours, 10% of
the total.
The resource is 100% so that means he worked 8am to 12 noon, then
stopped.
The task splits with the unworked portion moving to restart
Tuesday 8am.
When you enter 10% for Tuesday, work again proceeds from 8am to
12 noon and
then stops. (Resource is 100%, remember, so there's a 1:1
correspondence
between work accomplished and time passed.) As of the end of the
day
Tuesday Actual Duration is 1 day (not 2 days because at 4 hours
working time
per day it takes 2 calendar days to burn-up 1 duration day) and
remaining
Duration is 4 days; the remaining work is scheduled to resume
Wednesday at
8am. The result is that work is done in the mornings and the
afternoons
become non-working time (times inside splits are non-working -
the task goes
on 'vacation.') Non-working time does not count for duration so
although
the task elapsed time extends for another 5 days plus weekend,
the
non-working afternoons are backed out of the duration and so the
duration
remains at 5 days, 10 weekdays at 4 working time hours per day.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://project.mvps.org/faqs.htm for the FAQs
Hi all,
My scenario of a task, planned to take 5 days that instead
takes 10 days,
is
arbitrary. My point is that if, for whatever reason, I only do
half what
I
plan to do each day, that my 5 day task will take 10 days.
Given this,
the
duration should move from being 5 days to 10 days and my SV
should be
hugely
negative and anything but 0.
I should not have to enter anthing manually if all my options
are set in
advance and I prefer to only work from my task sheet.
Here's my list of steps:
1) Task set to Fixed Units with a duration of 5 days
2) Tools->Options->Calc has both Move checkboxes checked
3) I have one resource assigned at $125/hr or $1,000/day
4) I set my baseline
5) Each day I set % Work Complete equal to 10% which is only
half of what
I planned to do for the day
6) I now see a split task with the planned finish date moving
ahead by
half a day.
7) Each day I go to Project->Info and advance the current day
and status
day ahead by one day and then I add another 10% of work
complete once
again
moving the finish day ahead by half a day.
After doing only a half days work for 10 days, I have finally
finished my
5
days of work but my duration shows only 5 days whereas my gantt
chart
shows
duration to be 10 days.
Also, if I am 5 days late why is my SV equal to 0 since I am
late by 5
days.
Thanks,
glenn
:
Hi Glenn,
I think if you look at your Gantt chart, you'll see your task
has
been split several times. Project is assuming you only worked
4
hours (8:00 - 12:00) and has moved the remaining work to
recommence
the next morning at 8:00.
Have you tried recording actual work per day in either the
Task
Usage or Resource Usage view? That method will do what I
think you
are seeking. By the end of day 3 with only 12 hours of work
recorded, I show a 6.5 day duration and a negative SV. The
assignment units for the portion of the task with actual work
recorded has dropped to 50% and the actual 4 hours of work has
been
spread evenly throughout the entire 8 hour (1day) duration.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
Hi all,
I have a task with a 5d duration and 5d of work. If I
complete
only part of
my work each day, then my duration and/or finish date should
grow
accordingly.
In Tools->Options->Calculate, I check both Move check boxes.
There are
actually 4 move check boxes but I checked just the 2 that
are at
the top
level.
In day 1, I complete only 0.5d of work. This moves my
completion
date 0.5d
ahead. I next set my current date and status date in
Project->Information to
the next calendar date. On my second day, I complete only
0.5d of
work and
my completion date pushes the duration of the task ahead
another
0.5d which
should make my duration field equal to 6d but the duration
field
remains at
5d.
If I do only 0.5d of work each day, my task duration should
grow
from 5d to
10d. Instead my duration field remains at 5d and my final
SV is
0.
Can anyone tell me why my duration does not grow and my SV
does
not reflect
a blown schedule?
Thanks
glenn