J
Jesse Teichman
I have several tasks which have fixed durations, such as one month, but which
require a resource at 50%, which to me means about 20 working days at 4
hours/day. I have entered those tasks as '1 emon' to have the gantt reflect
the proper time frame. However, when I assign the resource, the emon treats
her as if she works 24 hours a day/7 days a week, even those I have set the
resource calendar type to 'standard.' This obiously results in many more
work hours than what is intended, and I can't understand why the resource
calendar type does not force the 'emon' function to recognize that this is a
person on a 40-hour week rather than a machine that is available 24/7. Any
ideas?
require a resource at 50%, which to me means about 20 working days at 4
hours/day. I have entered those tasks as '1 emon' to have the gantt reflect
the proper time frame. However, when I assign the resource, the emon treats
her as if she works 24 hours a day/7 days a week, even those I have set the
resource calendar type to 'standard.' This obiously results in many more
work hours than what is intended, and I can't understand why the resource
calendar type does not force the 'emon' function to recognize that this is a
person on a 40-hour week rather than a machine that is available 24/7. Any
ideas?