J
Jochem Davids
I will give a small example to illustrate my problem with making a planning
in MS Project:
In example:
A task has a (planned) duration of 5 days (from Start to Finish). An
employee (resource) will effectively work on this task (planned) for 2 days
to complete it.
In MS Project there is a column for filling in the (planned) duration and
filling in the actual duration. But it seems that I cannot fill in the
planned execution time.
My question: how can I make a distinction between (planned) duration and
planned execution time of a task.
In the calculation of scheduling a task the following formula is used:
Duration = Work / Units. It seems that MS Project doesn't take the planned
execution time into account.
Does anybody know how to solve this?
in MS Project:
In example:
A task has a (planned) duration of 5 days (from Start to Finish). An
employee (resource) will effectively work on this task (planned) for 2 days
to complete it.
In MS Project there is a column for filling in the (planned) duration and
filling in the actual duration. But it seems that I cannot fill in the
planned execution time.
My question: how can I make a distinction between (planned) duration and
planned execution time of a task.
In the calculation of scheduling a task the following formula is used:
Duration = Work / Units. It seems that MS Project doesn't take the planned
execution time into account.
Does anybody know how to solve this?