Duration/Work Fields

D

Diane

Using MS Project 2003:
Is there a way to enter a Duration field of 5 days, Work
field of 20 hours, and 2 Resources at 100%?

When I enter a Duration of 5 days, I get 40 Work hours.
Changing the Work hours to 20, changes the Duration to
3.14 days.

Thanks for your response!
 
J

John Beamish

1. Create the resources.
2. Double-click on each resource and change the working time for each to
2hr per day.
3. Create the task.
4. Set the "Type" to "Fixed Duration", set the duration to 5d, set the
work to 20hr.
5. Double-click on the task and assign the resources at 100% each.

But why?

Using MS Project 2003:
Is there a way to enter a Duration field of 5 days, Work
field of 20 hours, and 2 Resources at 100%?

When I enter a Duration of 5 days, I get 40 Work hours.
Changing the Work hours to 20, changes the Duration to
3.14 days.

Thanks for your response!



--
 
M

Mike Glen

Hi Diane,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series of Microsoft Project lessons in
the TechTrax ezine, particularly Lesson 11 - Task Types at this site:
http://tinyurl.com/2xbhc (Perhaps you'd care to rate it before leaving the
site, :) Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 