D
Diane
Using MS Project 2003:
Is there a way to enter a Duration field of 5 days, Work
field of 20 hours, and 2 Resources at 100%?
When I enter a Duration of 5 days, I get 40 Work hours.
Changing the Work hours to 20, changes the Duration to
3.14 days.
Thanks for your response!
Is there a way to enter a Duration field of 5 days, Work
field of 20 hours, and 2 Resources at 100%?
When I enter a Duration of 5 days, I get 40 Work hours.
Changing the Work hours to 20, changes the Duration to
3.14 days.
Thanks for your response!