Hi, i'm new to project and thought I'd got the hang of the work=duration x
units formula but project is not working as I thought it should.
I have a task that is 2 days duration with 2 people working at 100% and
project quite rightly shows 32hours work. When I look at the task usage it
shows Thursday at 4 hours Friday at 8 and Monday at 4 - (for each resource)
surely this is 3 days and not 2? None of the resources are allocated to
other tasks. Why didn't it allocated 8 hours on Thursday and Friday?
The task is effort driven although this shouldn't make a difference unless
I'm adding or emoving a resource yes?
I'd really appreciate an answer, my basic understanding of this is
obviously wrong
Thanks
Diane
units formula but project is not working as I thought it should.
I have a task that is 2 days duration with 2 people working at 100% and
project quite rightly shows 32hours work. When I look at the task usage it
shows Thursday at 4 hours Friday at 8 and Monday at 4 - (for each resource)
surely this is 3 days and not 2? None of the resources are allocated to
other tasks. Why didn't it allocated 8 hours on Thursday and Friday?
The task is effort driven although this shouldn't make a difference unless
I'm adding or emoving a resource yes?
I'd really appreciate an answer, my basic understanding of this is
obviously wrong
Thanks
Diane