duration

J

Jie

How can I change the task type? I can not change it. for example, I can not change the duration of T1.1
but I can change the task type of Task 1.1.1? Why

Thanks
 
G

Gérard Ducouret

Hello Jie,

The T1.1 task is probably a Summry task with some subtasks ?

Gérard Ducouret

Jie said:
How can I change the task type? I can not change it. for example, I can
not change the duration of T1.1,
 
G

Gérard Ducouret

Jie,

No : the duration of a Summary task is calculated by the software from the
durations of its subordinates, and from the links between them.

Gérard Ducouret
 
M

Mike Glen

The Duration of a Summary task is calculated by Project to be the working
time between the earliest start date and the latest fininsh date of the
subordinate tasks.

Mike Glen
MS Project MVP
 