Can a project duration of 180 days be shown as 6 months when only using a 5
day work week?
For example - the client asks for 180 days expecting a 6 months completion,
however it is shown as more like 8 months taking out the weekends. We want
to keep the weekends as non-working when figuring available hours, but don't
want to have to figure out the actual working days in 6 months.