In addition to Rob and Jan's comments, there is something called the
"8/80
Rule" that is handy to keep in mind. If your tasks are less than 8
man-hours you're probably unecessariy micromanaging. If your tasks are
more
than 80 hours in duration you're probably not breaking the work down
into
enough detail to effectively manage it. A 12 month duration task
really
fits into the latter category.
--
Steve House [Project MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs
How come when I put a start and finish date via the calendar that =
exactly
12 months, the duration is calculated as 13.85 months?
Thanks
Phil
--
Phil Holberton
MaxThera, Inc.
978-927-8900
(e-mail address removed)