bikerjohn
I created a 24 / 7 calendar and assigned it to a task. I also created a
local resource and assigned the 24 / 7 calendar to the resource. When I am
in a gantt view and I change a task calendar from the standard calendar to
the new 24/7 calendar, the end date of the task changes as expected but the
duration stays the same. The task types are fixed units. I assumed that the
duration would follow the task calendar and not the project calendar? If the
duration follows the project calendar is there a formula i can create to show
the actual task duration based on the task calendars?
local resource and assigned the 24 / 7 calendar to the resource. When I am
in a gantt view and I change a task calendar from the standard calendar to
the new 24/7 calendar, the end date of the task changes as expected but the
duration stays the same. The task types are fixed units. I assumed that the
duration would follow the task calendar and not the project calendar? If the
duration follows the project calendar is there a formula i can create to show
the actual task duration based on the task calendars?